(Atlantic) The Atlantic City Council had a light agenda on Wednesday night. One of the items on the docket was an order approving pay application #8 to TK Concrete in the amount of $48,130.00 for the West 22nd Street improvement project.
Dave Sturm of Snyder and Associates provided the council members with an update on the project.
Atlantic City Administrator John Lund says the total cost of the project is $ 1,421,207.75. He adds that there have been no change orders. The balance owed on the project is $262,120.00.